Forum topic by bscur posted 02-10-2012 08:56 PM 1413 views 0 times favorited 4 replies Add to Favorites Watch
View bscur's profile

bscur

17 posts in 1384 days


02-10-2012 08:56 PM

Topic tags/keywords: kitchen remodel sequence tile refinish order counter oak finishing sanding arts and crafts

I want to do the following things to my kitchen, what is the best order?

-Replace appliances (fridge, stove, microwave, dish washer)
-Refinish cupboards
-Have the counter tops done with granite
-Do the tile backsplash on my own

So what is the best order? Any ideas?
Thanks,
Brad


4 replies so far

View timb's profile

timb

4 posts in 1053 days


#1 posted 02-10-2012 09:03 PM

I think I would do the Cabinet refinishing first, then do the counter tops, tile splash then the appliances.

Tim

View AlaskaGuy's profile

AlaskaGuy

808 posts in 1055 days


#2 posted 02-10-2012 09:10 PM

If it was me, I’d pick out my appliance first. This way you know all the sizes and know they will fit you present kitchen. It will also help you decide if you want to change/remodel any of your existing cabinets. In many cases it’s possible to make an existing cabinet shorter or narrower(example, you may want a larger refrigerator. The counter top people will want the size of you new sink before they fabricate the counter.

Next I’d remove the old counters and make any change you might do. Then do the refinishing.

Now you can do the counter tops, and last the tile work. I’m assuming the tile work will sit on top of the counter top back splash.

-- Alaskan's for Global warming!

View DrDirt's profile

DrDirt

2597 posts in 2488 days


#3 posted 02-10-2012 09:10 PM

Cabinets first.

If you were going to change cabinets –
Make/buy the new ones before demolition.
Once you are ready with new cabinets – you can tear everything out and then work bottom to top –
repair floors – take the time to replace water shut-off valves that are coroded and not working so well

Install cabinets –
Then countertops
Then backsplash.

Then put in your new appliances.

Key is don’t trash the place til you have the replacements ready to go – or you will have a SUPER unhappy wife living in the construction mess.

-- "If we did all the things we are capable of doing, we would literally astonish ourselves." Edison

View Sawkerf's profile

Sawkerf

1730 posts in 1814 days


#4 posted 02-10-2012 09:20 PM

I do 3-4 kitchens a year, and would recommend the following sequence.

1. Select your appliances including sinks
2. Remove the old countertops
3. Get the granite guys in to make their template(s) You’ll be looking at a week, or two, for them to fabricate the new countertops. While they’re doing that;
5 Make any changes needed in your plumbing, electrical, etc.
6. Refinish your cabs.
7. Install the new appliances and do your backsplash after the new countertops are installed.

-- Adversity doesn't build character...................it reveals it.

Have your say...

You must be signed in to reply.

DISCLAIMER: Any posts on LJ are posted by individuals acting in their own right and do not necessarily reflect the views of LJ. LJ will not be held liable for the actions of any user.

Latest Projects | Latest Blog Entries | Latest Forum Topics

HomeRefurbers.com

Latest Projects | Latest Blog Entries | Latest Forum Topics

GardenTenders.com :: gardening showcase