New Shop building! #4: Ramping up the efforts. (more pic's again)

  • Advertise with us
Blog entry by JoeinGa posted 06-07-2014 08:23 PM 1264 reads 0 times favorited 5 comments Add to Favorites Watch
« Part 3: Little bit o' progress... Stairway to Heaven (lots of pic's again) Part 4 of New Shop building! series Part 5: ARRR! ARRRGH! MORE POWER! (apologies to Tim the toolman Taylor) »

Well, Georgia Power came out this week for their “site inspection”. Wow, looks like it might cost me a small arm (and possibly a leg) to get the power hooked up. I mentioned in the last part that back when we lived over on the other side of the state, Georgia Power Company came and dropped a pole in my yard about six feet from my shop. They didn’t charge me a thing for doing that and they also put a dedicated meter there for the shop. We always got two bills, one of which was addressed as “Durning Barn”. THAT bill only ran me about $15 or $20 a month. (As a reference point, this was back in 1994)

Fast forward to now and the guys that came to the house said they no longer put power poles in at no charge. The now have some convoluted way of figuring out how much power I might “potentially use” over the next 3 years, then they figure out what it’s going to COST THEM to bring the power to my shop. I have to cover the difference IN ADVANCE before they’ll come and drop the pole in my yard. Based on what I told them I have in equipment, they figure I’ll probably use between $40 and $50 a month. I couldn’t pin the guy down to a figure because he said he has to go back and get with the engineers to figure it all out. He did tell me that he’s been doing this for almost 15 years and “Off the record” he said it could POSSIBLY cost me somewhere between $1200 and $3000 out of pocket UP FRONT to get the power hooked up.

YIKES! That’s gonna take a BIG BITE outta the ol shop budget! So I’m guessing a table saw and a lathe will NOT be new additions to my tools any time soon. But I’m in this now, so I GOTTA move forward best I can!
.

So as to progress… I got the cruddy looking doors painted dark gray. Found a can of Rustoleum marked down half off at Wally World because it was dented. THAT was a great bargain!

.


.

and I got the rest of the pressure treated 1” X 6” boards put up all around the outside. They’ll also be painted the same dark gray as the doors. Their MAIN FUNCTION will be to hold the skirting on (that’s why they almost touch the ground), but by doing it this way, they’ll blend in as trim pieces. And if I ever need to get under the building, all I’ll have to do is unscrew one 12’ piece of skirt to gain access. I’ll probably re-paint the rest of the building light gray (if I have any budget dollars left).

.

I got the carpeting pulled out. A guy I work with was thrilled to take it. He also hauled away the 2 trailer tongues to sell as scrap. I dont plan on having to move this thing ever in MY lifetime!

.

.


.

My big success this week was getting the ramp built. It’s almost 11’ long and it’s 4’ wide. I used 1 X 10 pressure treated lumber and at the bottom end I put solid cap-blocks below ground level for the stringers to sit on. I could drive a truck up this thing, it’s that strong!
.
.

I also noticed how much the stairs/landing has yellowed in just 2 weeks as compared to the new pressure treated ramp wood being so green.
.
.
Once I get the gap closed up that runs the center of the floor, I can start moving my STUFF in. You can see where I used expanding foam to fill in between the floor joists, but the way it was built the top boards still have a gap. The flooring (yes, REAL plywood, not that particle board crap) is 3/4” thick, and the gap is just under 3”. So I’m just gonna slice off any excess foam with a steak knife and use 1” X 3”’s which will work nicely. Then I’ll put the aluminum runner back down that covered the carpet seam.
.

.

.
.
Well that’s about it for this update. Stay tuned kids! Same Bat time, same Bat channel

-- Perform A Random Act Of Kindness Today ... Pay It Forward



5 comments so far

View Monte Pittman's profile

Monte Pittman

15488 posts in 1089 days


#1 posted 06-07-2014 08:34 PM

Crazy about the power pole. They still put it in free here (we pay for the power). Everyone wants their share of your money.

Good to see your progress. Hope you get shop running soon.

-- Mother Nature created it, I just assemble it.

View NormG's profile

NormG

4537 posts in 1754 days


#2 posted 06-07-2014 09:06 PM

DO you have to have a pole?

A friend of mine who lives over in Jesup, purchased a FEMA double wide at auction and they just put the meter on the outside of the building.

Great progress though

-- Norman

View gfadvm's profile

gfadvm

11536 posts in 1441 days


#3 posted 06-08-2014 12:59 AM

Great progress but very disappointing about the cost of getting power to it. Do you have options: run a line from the house? That just seems way high what they quoted you.

-- " I'll try to be nicer, if you'll try to be smarter" gfadvm

View doubleDD's profile (online now)

doubleDD

2813 posts in 794 days


#4 posted 06-08-2014 02:38 AM

I hope the anticipation of moving tools in soon will offset the pressure of the high cost of other things. Can’t wait to see the completed set up. Walk slowly and carry a heavy stick.

-- --Dave, Downers Grove, Il. When you run out of ideas, start building your dreams

View JoeinGa's profile

JoeinGa

3694 posts in 758 days


#5 posted 06-08-2014 02:25 PM

Yep, the “cheaper” way is overhead lines. And it’s over 160’ (in a straight line) from the nearest power source. Have 2 GIANT Pecan trees in the direct line-of-sight that I dont want to take out, so they’ll actually put 2 poles in. One will be a straight shot to the corner of my back yard, and the second one will cross to the other side of the property at the building. It’s over 260’ to go that way. If they go underground, they still cant go “straight line” because they’d be running thru my septic drain field. Underground will be a bit shorter but not too much. They tell me it’s much more $$ to go underground, that’s why such a large spread in his price guess.

Ga Power will NOT allow me to connect to the existing meter. Says it’s “not legal” because the meter on the house cant carry the extra load of woodworking tools …. I’m gonna check with an electrician to see if that’s correct.

I’m going to check about renting a DitchWitch and digging the ditch myself. Rent is about $200 for 1/2 day (four hours). Need to see if Ga Power will let me do that myself and how much it’ll save me (if any)

-- Perform A Random Act Of Kindness Today ... Pay It Forward

Have your say...

You must be signed in to post the comments.

DISCLAIMER: Any posts on LJ are posted by individuals acting in their own right and do not necessarily reflect the views of LJ. LJ will not be held liable for the actions of any user.

Latest Projects | Latest Blog Entries | Latest Forum Topics

HomeRefurbers.com

Latest Projects | Latest Blog Entries | Latest Forum Topics

GardenTenders.com :: gardening showcase